| COMPANY EXPERIENCE FOR THE
LAST SEVEN YEARS |
NO |
PROJECT
NAME |
OWNER |
PROJECT DESCRIPTION |
ORIGINAL CONTRACT VALUE (QR.) |
ORIGINAL START DATE |
COMPLETION DATE |
1 |
Development works at QATAR CENTRAL BANK |
QATAR CENTRAL BANK |
Construction of Boundary Wall & external shaded parking for Qatar Islamic Bank |
14,000,000 |
01.11.2008 |
05.02.2009 |
2 |
Metropolitan Hotel Extension Building |
Ibrahim Al Asmakh |
Construction and Completion of B+G+6 Storey Hotel with total built up area of 25,309 m2 |
90,628,667 |
01.08.2007 |
31.12.2008 |
3 |
Construction of 7 Schools Building |
Ashgal |
Construction of 7 Schools (main bldg. and external works) for Boys & for girls at Umm salal ,Bani hajar & Nasryeh with total built up area of 9,068 m2 for each |
339,000,000 |
27.08.2007 |
31.08.2008 |
4 |
Ministry of Finance & Carpark |
Ashgal |
Renovation and Maintenance of existing bldg consisting of basement, ground floor & 3 floors and construction of new office building & car parks buildings with total built up area of 7,565.64m2 |
126,000,000 |
Governt. |
01.11.2008 |
5 |
Commercial Center at Hetmi (3B+G+M+15) |
Skh Hamad Bn Jassim Al-Thani |
Office Building at Hetmi Area (3B+G+M+15) of 28,263m2 area |
72,976,000 |
01.06.2005 |
01.07.2007 |
6 |
Al-Rayyan Tower (B+G+M+19) at west bay |
Mr. Zaieed Bin Saeed Al Khaireen |
Res. Tower at west bay (B+G+M+19) of 30,202 m2 area |
122,000,000 |
01.07.2005 |
01.06.2007 |
7 |
Qatar News Agency |
Qatar News Agency |
Finishing & maintenance works |
3,750,000 |
01.06.2006 |
01.04.2007 |
8 |
Ibrahim Asmakh Palace |
Mr. Ibrahim Al -Asmakh |
Construction of Palace, Majlis and external works. |
8,400,000 |
01.10.2006 |
01.04.2007 |
9 |
Private Palace & Majlis |
Sh. Abdul Aziz Bin Nasser Al Thani |
Completion of Palace and Majlis |
10,000,000 |
01.08.2006 |
01.02.2007 |
10 |
Al Asmakh Tower (B+G+25) Movenpick Hotel |
Al-Asmakh RealState |
Movenpick Suites Hotel at West Bay of total built up area 37,335 m2 |
176,000,000 |
27.07.2004 |
30.09.2006 |
11 |
B+G+M+11 Development at Ghanim Al Qadeem |
Mr. Haidar Suliman Haider |
Four Residential Bldg. of 53,872 m2 & 286 flats at Ghanim Qadeem |
80,698,000 |
15.08.2004 |
15.08.2006 |
12 |
Regency Tower (B+G+25) |
Mr. Ibrahim Al-asmagh |
Residential Tower at West Bay o 171 flats, Built up area 41,584m2f |
125,000,000 |
01.11.2004 |
01.07.2006 |
13 |
(B+G+6) Residential Building (2) at Al-saad |
Sh. Hussa Al-thani |
Residential building of 67 flats atAl-saad |
15,243,121 |
01.02.2004 |
01.10.2005 |
14 |
Private Villa at Markhiya |
Sh. Ameena Bin Nasser Al Thani |
Private Villa at Markhiya |
1,000,000 |
01.10.2004 |
01.10.2005 |
15 |
Furniture, Fittings & Equipment for PWA (B+G+16) |
Public Works Authority (ASGHAL) |
Management, Finishing & Furniture for PWA Asghal Tower Headquarters |
21,679,716 |
10.04.2005 |
07.09.2005 |
| 16 |
(B+G+6) Residential Building at Saad |
Sh. Abdul aziz Al-thani |
Residential Building of 53 flats at Al-saad |
9,866,762 |
01.02.2004 |
01.08.2005 |
| 17 |
(B+G+6) Residential Bldg.(3) At Al-saad |
Sh. Hussa Al-thani |
Residential Building of 66 flats at Al-saad |
14,643,031 |
01.02.2004 |
01.07.2005 |
| 18 |
Al Asmakh Retail Mall Complex at Al Saad |
Al-Asmakh Real State |
Retail Complex of 36,179m2 area at al saad |
46,472,025 |
25.05.2004 |
20.06.2005 |
| 19 |
33 Villas (Beverly Hills Phase III) |
Sh. Khaled Al Thani |
Third phase of large villas complex (33 villas) |
17,000,000 |
11.2003 |
01.05.2005 |
| 20 |
Grand Regency Hotel |
Ibrahim Al Asmakh |
Construction of Storey furnished suits hotel bldg. |
23,200,000 |
13.11.2003 |
13.04.2005 |
| 21 |
Beverly Hills Tower (Piling Cont.) |
Mr. Ibrahim Al Asmakh |
Piling works for Beverly Hills Tower |
6,400,000 |
10.08.2004 |
24.11.2004 |
| 22 |
55 Villa complex + club house + ancillary |
Ali Al Malki |
Construction of 55 villas of total built up area 14,300m2 |
15,500,000 |
01.09.2003 |
01.11.2004 |
| 23 |
Office Bldg. At C-ring road |
Sh. Ahmad Bin Khalifa Al-Thani |
Commercial Building at C ring road |
7,000,000 |
09.07.2003 |
09.07.2004 |
| 24 |
44 Villas complex + clubhouse + ancillary |
Ali Al Malki |
Construction of 44 villas of total built up area 14,300m2 |
13,000,000 |
22.04.2003 |
22.04.2004 |
| 25 |
Beverly Hills Compound 49 Villas (Phase 2) |
Sh. Khalid Bin Nasser Al-Thani |
Construction of 49 Villas & Ancillaries |
22,600,000 |
24.06.2003 |
2004 |
| 26 |
Beautification of Al-Markhiya st. |
BED |
Soft & Hard landscaping works |
3,007,803 |
16.03.2002 |
21.11.2003 |
| 27 |
Commercial Bldg for Sh. Abdel Azziz Al Thani |
Sh. Abdel Aziz Al Thani |
Commercial Building at C ring road |
4,650,000 |
14.01.2002 |
05.05.2003 |
| 28 |
Asma Bint Abu Baker School at Sadd Area |
BED |
Construction of school for girls at Alsadd |
17,231,454 |
11.12.2001 |
20.03.2003 |
| 29 |
Private Villa |
Mr. Rashid Al-Sulaiti |
Skeleton works of private Villa |
1,500,000 |
01.08.2003 |
2003 |
| 30 |
Majlis for Sh. Jassim Bin Abdulla Al Thani |
Sh. Jassim Bn Abdulla Al Thani |
Construction of Majlis |
2,250,000 |
07.02.2001 |
25.09.2002 |
| 31 |
64 Villas Compound |
Khalid Bin Nasir at Dafna |
Construction of 64 Villas & Ancillaries |
43,000,000 |
28.02.1999 |
09.09.2002 |
| 32 |
Apple Bee Restaurant |
Sh. Mohd. Al-Thani |
Construction of Apple Bees restaurant |
2,450,000 |
19.02.2002 |
12.06.2002 |
| 33 |
Res. Villas Compound at Al Wakir |
Sh. Jassim Al Mahmoud |
Construction of Villa compound & Ancillaries |
2,150,000 |
01.11.2001 |
15.11.2001 |
| 34 |
LULU Shopping Center Complex |
Sh. Hassan Bin Khalid Al-Thani |
Construction of LULU Hypermarket |
20,750,000 |
05.02.2000 |
06.06.2001 |
| 35 |
Guest House Renovation and Maintenance |
Dewan Al-Amiri |
Construction & Renovation of Guest House |
3,245,000 |
14.08.2000 |
03.02.2001 |
| 36 |
Res. Compound for Sh. Abdel Rahman Al Manai |
Sh. Abdel Rahman Manai |
Construction of residential compound |
10,500,000 |
11.08.1999 |
11.10.2000 |
| 37 |
Three Res. Bldg. at Old Airport |
Sh. Jassim Al Mahmoud |
Construction of three residential Bldg |
2,875,000 |
15.08.1998 |
15.01.2000 |
| |
|
|
TOTAL COMPLETED PROJECTS |
1,495,666,579 |
|
|
| IN HAND PROJECTS |
NO |
PROJECT
NAME |
OWNER |
CONSULTANT |
DURATION |
PRIVATE
/GOVT. |
SCOPE OF WORK |
START DATE |
COMPLETION DATE |
PROJECT PRICE QR. |
| 1 |
Barwa Utility Compound |
Barwa |
Maunsell |
410 Days |
Private |
Construction of seven numbers of different utility buildings of total built up area = 6632 m2 at Barwa city at abu hamour |
1/1/2009 |
13/2/2010 |
39,000,000.00 |
| 2 |
Construction for additional four floors to existing (G+1) Office building & construction of( G+ 3 )Car park building |
Dr Youssef Al Qaradawi |
United Consultants |
15 months |
Private |
Construction for additional four floors to existing (G+1) Office building & construction of (G+ 3) Car park building at al sadd area ,total built up area = 11,000 m2 |
05/06/08 |
05/09/09 |
38,000,000.00 |
| 3 |
Construction of private palace for Sh Hessa Al Thani at WAAB area |
Sh Khalid Bin Nasser / Sh Hessa Al Thani |
GHD |
14 months |
Private |
Construction of Two Villas , Women Majlis ,Men Majlis ,Service Building & ancillaries with a total built up area = 6380 m2 |
01/07/08 |
01/08/09 |
37,300,000.00 |
| 4 |
B+G+9Floors at Musherib |
Sh. Hussa Bin Seif Al Thani |
EHAF |
18 Months |
Private |
Construction of Residential Building of B+G+9 Floors at musherib |
3/5/08 |
3/10/09 |
28,500,000.00 |
| 5 |
B+G+10 Floors |
Sh. Faisal Bin Nasser Al Thani |
EHAF |
18 Months |
Private |
Construction of Residential Building of B+G+10 Floors at musherib |
3/5/08 |
3/10/09 |
32,740,850.00 |
| 6 |
Commercial & Res. Bldg. at al-mirqab al-jadid |
Mr. Ali Bin Hamad Al Attiyah |
Qatar Design Consertium |
18 Months |
Private |
Construction and Completion of 2 buildings commercial and residential (two basement+ground+mezzanine+eight/seven typical floors & penthouse)with total built up area of 42,000m2 |
01.02.08 |
01.02.09 |
160,000,000.00 |
| 7 |
Office Tower (2B+G & 38 Floors) |
Sh. Abdullah Bin Khaled Al Thani |
Syna |
24 months |
Private |
Construction of Office Tower located at Doha Haditha (2B+G&38 Floors) of total built up area of 63,048 m2 |
16.12.06 |
1.04.09 |
186,000,000 |
| 8 |
Construction of 92 villas & 12 Res. Bldg |
Ramco Trad. & Contg. |
James Cubitt & Partners |
15 months |
Private |
Construction of 92 villas 12 shops, 12 Res. Bldgs. & Ancillaries at Omm salal with total built up area of 32,167 m2 |
4.2007 |
01.10.08 |
144,000,000 |
| |
TOTAL FOR IN-HAND PROJECTS |
665,540,850.00 |
| IN HAND PROJECTS - RAMCO LIBYA |
NO |
PROJECT
NAME |
DESCRIPTION |
COMPLETION
DATE |
LOCATION |
PROJECT AMOUNT EURO |
| 1 |
Africa Hotel Tower at North Of Al-Ghiran at Tripoli / Libya Five Star Hotel |
Two basements for 197 car parking ,five numbers of staircase , 6 numbers of lifts.
Ground Floor consists of 7 nos of Shops, 1 business center, 3 coffee shops, 1 reception, 2 coffee bars, 2 bars , lounge, storage and facilities rooms.
1st Floor consists of 1 Business center, 1 kitchen, 1 Restaurants includes storages, Chillers, Freezers.
2nd Floor consists of 1 Restaurants, 1 Kitchen, 2 Swimming pool, 1 Fitness center, 4 Massage, 3 Sauna, 4 Steam room
Typical floors will Accommodate 3 Royal suits 20 Junior Suits, and 332 rooms.
The Services Floor Consists of Reception, Restaurant, Cafés, and Administration, Offices, Business center, medical center & Kitchens.
19th floor consists of one Bar, one Kitchen, one Restaurant |
20 Months starting from 01/02/09 |
North Al- Ghiran at Tripoli - Libya |
100,000,000 |
| 2 |
Great Multipurpose Hall project at North Al- Ghiran at Tripoli - Libya |
Ground floor with internal pillar free structure, 130 m long, 76 m wide & 10 m high. The height to be free from obstructions between the ground & the twin domed ceiling
Ceiling & perpendicular side walls (Insulated & color painted)
Central air conditioned installatio
Parking for 630 cars on one underground floor.
|
16 Months starting from 01/02/09 |
North Al- Ghiran at Tripoli - Libya |
35,000,000 |
| 3 |
Zawra Hotel at Libya Five Star Hotel & Resort (G + M + 5 Floors) |
Ground floor Room : 5 numbers of Lobbies , 5 numbers of Restaurants , 4 numbers of Offices & 6 nos of Lifts ,shops, coffee shops
Mezzanine Floor Office : 8 Numbers of Restaurants ,2 numbers of lobbies.
Hard & Soft landscaping works (swimnming pool & fountains)
|
18 Months starting from 01/02/09 |
Zawra/Libya |
50,000,000 |
| 4 |
Five Star Hotel at Bin Ghazi (B+G+M+6) |
Construction and Completion of 8 floors hotel building + one basement consists of 356 luxury rooms and 4 Royal suites and 40 suites for VIP visitors, health club and gym and tennis court. |
20 Months |
Bin Ghazi / Libya |
123,478,500 |
| 5 |
Tripoli Gate |
Construction and completion of 28 residential buildings. |
20 Months |
Tripoli Libya |
50,000,000 |
| |
TOTAL FOR IN-HAND PROJECTS |
358,478,500.00 |
|
|
|
|
|
© 2008 RAMCO, all rights reserved. |
|
| Civil & Architecture Building, Private compound Villas, Towers, Office Towers, Industrial and Commercial Building , Maintenance Works Landscaping Projects. AL ASMAKH TOWER, REGENCY TOWER, AL RAYYAN TOWER |
|
|